Garacad Port & Town Construction Project

repo

Bantu Liberation Movement
VIP
Work was stalled for 4 months in the summer due to the monsoon season.

Divers will arrive in a few days to guide the antifer placements.

Work on the small 100 meter berth has begun. The 2x200m berths will be done once the breakwater is done. There will be a 100 meter extension after that.

 

Hassan Garguute Buldanana

AUG 25, 2023
VIP
Work was stalled for 4 months in the summer due to the monsoon season.

Divers will arrive in a few days to guide the antifer placements.

Work on the small 100 meter berth has begun. The 2x200m berths will be done once the breakwater is done. There will be a 100 meter extension after that.

:rejoice:You were spot on about the divers mudane, guul inshalllah
 

Thegoodshepherd

Galkacyo iyo Calula dhexdood
VIP
This is serious work. Very impressed with how it is all progressing. The causeway seems to be bigger than I thought. Placing the blocks in place will stop erosion and will help reduce wave action. I hope they build a breakwater when the port is finished inshallah.
 

repo

Bantu Liberation Movement
VIP

The antifers will be lined up like this so the berth can be constructed on the other side.